Gas Pipeline Components

The Yallourn Gas Pipeline consists of the following components:

  • An off-take from the Longford to Dandenong Gas Transmission Pipeline
  • A custody transfer meter & communications hut 
  • Pig launcher and fenced compound at the tie-in location
  • A buried cross country gas transmission pipeline of approximately 500mm diameter, 8km in length and up to 10.2 MPa, including
    • a directional drilled crossing of the Latrobe River
    • bored road and pipeline crossings
    • an end point at the gas-fired power station
  • Gas conditioning & pig receiver facilities Design life will be 30 years

Proposed Pipeline Route

The proposed gas pipeline route is located on Crown land and EA owned land, largely within road reserves. This route has been selected to minimise impacts on private property and the environment, while limiting route length and ensuring acceptable constructability.

Rich text

Timing and Next Steps

Key activities and indicative timing for the Yallourn Gas Pipeline are:

 May-June 2026Approval of the Pipeline Consultation Plan
 June-July 2026Environmental assessments including field surveys and engagement with landowners
 From August 2026Preparation and submission of the Pipeline Licence Application

EA will work closely with landowners and occupiers to agree on land access conditions and manage survey work. Once EA has submitted an application to construct and operate a pipeline, a Notice of Pipeline application and details on how to provide a submission will be published.

Rich text

Contact Us

If you have any questions or would like to learn more about the Yallourn Gas Pipeline, please get in touch through the contact details below. Visit us in person at our Community Hub - 228 Commercial Road Morwell. Open Wednesdays, 10am-3pm, or by appointment.

Community.yallourn@energyaustralia.com.au
1800 574 947
PO Box 444, Moe, Victoria, 3825
www.transformingyallourn.com.au

Title
Pipeline Consultation Plan

Name
EnergyAustralia Yallourn Gas Pipeline PCP.pdf

Title
Appendices

Name
Appendix 1 - Land Owner Rights.pdf
Document
Name
Appendix 2 - Statutory Authorities.pdf
Name
Appendix 3 - Pipeline Development.pdf
Name
Appendix 4 - Glossary of Terms.pdf
Document
Name
Appendix 5 - S19 Letter.pdf
Document
Name
Appendix 6 - S27 Letter.pdf
Document
Name
Appendix 7 - Communications Log.pdf
Name
Appendix A - Fact Sheet Overview.pdf
Name
Appendix B - Fact Sheet Impacts.pdf
Name
Appendix C - Fact Sheet Construction.pdf
Name
Appendix D - Fact Sheet Field Surveys.pdf
Rich text

Published date stamp 10 July 2026

Let's stay connected

Sign up for updates, ask a question or have your say.

Subscribe now

 

EnergyAustralia’s Yallourn Power Station and Mine operate on the lands of the Brayakaulung people of the Gunaikurnai nation. We acknowledge them as Traditional Owners and recognise their living culture and strong connections to their Country.